Steel Melt Shop Structure

Tata Steel [PLACEHOLDER]

Challenge

A running steel melt shop expansion: 42 m tall bay columns and 32 T crane girders erected within metres of live EOT crane operations, with steel deliveries constrained to night windows.

Approach

We shop-assembled columns in two-piece splices to cut height work by 40%, match-marked every assembly, and sequenced erection bay-by-bay against the client's production calendar. Every lift over 20 T ran on an engineered lift plan signed off 72 hours ahead.

Result

12,400 MT erected in 18 months, dimensional survey within ±3 mm on crane rails over a 180 m run, zero lost-time incidents across 1.1 million man-hours.

Spec Sheet

Scope
Fabrication + erection of SMS building & crane girders
Tonnage
12,400 MT structural steel
Duration
18 months
Contract type
Item-rate with free-issue steel
Key equipment
400 T crawler crane, SAW gantries, 96 m hook height
Peak manpower
640
Steel Melt Shop Structure — annotated technical viewBAY HT: 42MCRANE GIRDER: 32TRAIL TOL: ±3MM

Site record [PLACEHOLDER — replace with project photography]

Next project

Captive Power Plant — BTG Structures

A PROJECT LIKE THIS ON YOUR BOOKS?

Request a Quote

Estimation team replies in 2 business days