Power · Ramagundam, Telangana · 2022
ESP & Duct Revamp — Thermal Station
NTPC [PLACEHOLDER]
Challenge
A fixed 42-day outage with liquidated damages: 790 MT of corroded internals out and 860 MT of new collecting systems in, all inside a live station's ESP casing.
Approach
Hour-by-hour shutdown schedule rehearsed on a 3D sequence model; pre-fabricated internals staged in erection order in a marshalling yard; three-shift working with dedicated rigging crews per gas pass.
Result
Unit returned to service on day 41 — one day early. Emission performance test passed on first attempt.
Spec Sheet
- Scope
- Dismantle + replace ESP internals & flue ducting
- Tonnage
- 860 MT in / 790 MT out
- Window
- 42-day unit shutdown, fixed
- Contract type
- Shutdown works, LD-backed
- Key equipment
- Tower cranes inside ESP casing, gantry systems
- Peak manpower
- 480 across 3 shifts
Site record [PLACEHOLDER — replace with project photography]
Next project
Steel Melt Shop Structure
A PROJECT LIKE THIS ON YOUR BOOKS? →
Request a Quote
Estimation team replies in 2 business days