ESP & Duct Revamp — Thermal Station

Power · Ramagundam, Telangana · 2022

ESP & Duct Revamp — Thermal Station

NTPC [PLACEHOLDER]

Challenge

A fixed 42-day outage with liquidated damages: 790 MT of corroded internals out and 860 MT of new collecting systems in, all inside a live station's ESP casing.

Approach

Hour-by-hour shutdown schedule rehearsed on a 3D sequence model; pre-fabricated internals staged in erection order in a marshalling yard; three-shift working with dedicated rigging crews per gas pass.

Result

Unit returned to service on day 41 — one day early. Emission performance test passed on first attempt.

Spec Sheet

Scope
Dismantle + replace ESP internals & flue ducting
Tonnage
860 MT in / 790 MT out
Window
42-day unit shutdown, fixed
Contract type
Shutdown works, LD-backed
Key equipment
Tower cranes inside ESP casing, gantry systems
Peak manpower
480 across 3 shifts
ESP & Duct Revamp — Thermal Station — annotated technical viewWINDOW: 42 DAYS3 SHIFTS · 480 CREWRTS: DAY 41