Cement Grinding Unit

Cement · Solapur, Maharashtra · 2022

Cement Grinding Unit

UltraTech [PLACEHOLDER]

Challenge

A compressed 16-month first-dispatch target on a greenfield site with black-cotton soil demanding deep foundations under the mill and silo blocks.

Approach

Piled foundations ran round-the-clock in two rigs while the silo slipform crew mobilised early; the 52 m cement silo was slipformed in a continuous 21-day cycle.

Result

First cement dispatched 16 months from the first pile — the client's fastest grinding-unit build to date [PLACEHOLDER — confirm].

Spec Sheet

Scope
Civil + structural + equipment erection for grinding circuit
Tonnage
3,200 MT steel · 28,000 m³ concrete
Duration
16 months
Contract type
Composite works contract
Key equipment
Slipform rig, 150 T crawler crane
Peak manpower
560
Cement Grinding Unit — annotated technical viewSILO: 52M SLIPFORMCYCLE: 21 DAYSPILES: 1,240

Site record [PLACEHOLDER — replace with project photography]