Airport Terminal Roof Structure

Infrastructure · Visakhapatnam, Andhra Pradesh · 2025–26

Airport Terminal Roof Structure

L&T Construction [PLACEHOLDER]

Challenge

84 m clear-span trusses, each 118 T after pre-dressing, lifted over a partially built terminal with tandem cranes on a deck with strict ground-bearing limits.

Approach

Trusses ground-assembled on jigs with camber verified by total station, pre-dressed with purlins and walkways, then set in engineered tandem lifts with load-share monitoring.

Result

Seven trusses erected to date; camber survey on every set truss within 8 mm of theoretical. Completion scheduled Q2 2026.

Spec Sheet

Scope
Fabrication + erection of long-span roof trusses
Tonnage
2,900 MT
Spans
84 m clear, 12 primary trusses
Contract type
Subcontract to EPC
Key equipment
2 × 400 T crawlers in tandem, strand jacks
Status
Erection in progress — 7 of 12 trusses set
Airport Terminal Roof Structure — annotated technical viewSPAN: 84MTRUSS: 118TCAMBER: ±8MM

Site record [PLACEHOLDER — replace with project photography]

Next project

ESP & Duct Revamp — Thermal Station